01 Mar 2012 08:03:33

Offshore wind: an extremely risky business



It takes approximately 4 years and about £1000 per KW installed to develop a project in shallow waters (5–10m deep) in the offshore wind industry. The cost to ensure such a development depends on several factors and can account for as much as 20 per cent of the developers' budget.

The reason behind these high numbers can be found in the complex offshore supply chain and logistics [the sheer number of logistical interfaces which make the task of the project management inherently risky], the difficulty of securing finance in the current economic situation and much more.

These risks are manageable but they need to be shared evenly between developer and contractor. However, contractors avoid discussing risk for fear of losing out on work in a competitive environment. Rather, they are keen to win work in the nascent offshore sector and develop experience and a track record that will secure in-going contracts as the industry evolves.

Felix Würtenberger, director commercial steering BU offshore wind projects, Vattenfall Europe Windkraft GmbH says "In the future, only those willing to take and able to manage offshore risk will be able to build profitable offshore wind farms”. Fortunately help is at hand. A B2B conference is running this June so you can seize the opportunity to meet likeminded executives involved in offshore wind risk.

Tom Evans, managing director of Wind Energy update [the company behind this pioneering event] says "for the last 12 months we've heard, read and seen the results of poorly managed risk in the offshore wind industry. Some countries are now falling behind in their path to hit EU 2020 targets for wind generation and offshore wind risk is linked as a reason why".

With representatives from Fitch Ratings, Stadtkraft, RWE, Vattenfall and Siemens all talking opening about their work on risk identification and mitigation this is the must attend B2B event of 2012. Raising capital and permitting risks, project delivery risks and supply chain risk are all on the agenda.


Discussion Thread  

 


Related Categories

Clicking a category below will direct you to a list of related information

Skip Navigation Links.

Wind Energy Update Community



Linked Items From Wind Energy Update


  1. With 6,810 megawatts of wind capacity connected to the U.S. grid in 2011, wind operators will...

    22 Feb 2012
  2. There are less than four weeks before key industry figures from The EU Parliament, The Crown...

    13 Feb 2012
  3. With the on-going uncertainty over the production tax credit (PTC) extension, many factors are...

    13 Feb 2012
  4. Maintenance practices on wind turbines are primarily either 'preventative' actions performed at...

    31 Jan 2012


Related Items From Everyone


  1. European Eco-label, known as ‘the flower’ is awarded to selected Daikin Altherma ranges, being...

    22 Nov 2013
  2. PV Insider webinar examines the key challenges that developers and EPC groups are facing to...

    29 Aug 2012
  3. A reduced demand for fossil fuels saw carbon dioxide (CO2) emissions produced by the UK energy...

    30 Jul 2009
  4. Scottish Power Renewables' Whitelee Windfarm, the largest onshore wind power project in Europe,...

    21 May 2009



Go To Home

Resource Links

We're social: View Available Feeds Find out more! Leave us your feedback

RSS



We appreciate all feedback. Please leave as much or as little as you like about any aspect of this website.

If your message requires a response, please leave your email address.